Ludlow Road Open Space Improvement Works

Share Ludlow Road Open Space Improvement Works on Facebook Share Ludlow Road Open Space Improvement Works on Twitter Share Ludlow Road Open Space Improvement Works on Linkedin Email Ludlow Road Open Space Improvement Works link

The Council are looking to improve public accessibility and safety within Ludlow Road Open Space through constructing an all-season perimeter access pathway. Which followed from a consultation that occurred with the local residents and park users in early 2024.

Working with the Friends of Ludlow Road Open Space, the Council have secured funding to deliver:

  • Footpath around the perimeter of the park and through the woods

  • Boardwalks from recycled plastic

  • Some minor clear out works in the woods to open the space

  • Entrance paths improvements

  • Newly planted tree lined path section to create shade

  • Installation of new bins and benches

The team contracted Maydencroft to deliver these improvements. Several site visits were scheduled throughout the lifecycle of the project with locals and park users giving them the opportunity to learn more about the works taking place.

Once works are fully complete, a launch event will take place autumn/winter 2025.

More information to follow

Project updates:

July 2025 Update*

  • Boardwalk is complete
  • Gravel pathway almost complete
  • Street furniture locations confirmed, due to be installed.

Due to certain events occurring over the summer and the unpredictable weather conditions, project completion is now expected to be in autumn 2025.

May 2025 Update*

  • Tree planting almost complete, final tree planting to be done winter 2025 with the friends.
  • Breedon gravel is being laid out on sub-base along the pathway
  • Boardwalk complete
  • Swales complete
  • Project completion still aiming for Summer 25

(Photos of the pathway, boardwalk and tree planting)

March 2025 Update*

  • Tree planting has begun, with a community planting day held Tuesday 25 February where 15 trees were planted by residents, friends of Ludlow Road Open Space, Councillors, Countryside team and the Parks team. Facilitated by Maydencroft.
  • The subbase for the perimeter pathway has been completed and progress has been made on the boardwalk.
  • The project is expected to be complete by Summer 2025.

November 2024 Update*

Due to the wet weather conditions the completion works have been pushed to end of January.

August 2024 Update*

Ludlow Road Open Space Perimeter Pathway is progressing as per schedule. Maydencroft have been on site for almost a month and have been busy laying the foundations for the beginning of the path network. They have been clearing through some vegetation to join up the path networks near Sycamore Close and will be conducting some minor vegetation clearances through the woodland to allow for the beginning of the boardwalk to commence.


The Council are looking to improve public accessibility and safety within Ludlow Road Open Space through constructing an all-season perimeter access pathway. Which followed from a consultation that occurred with the local residents and park users in early 2024.

Working with the Friends of Ludlow Road Open Space, the Council have secured funding to deliver:

  • Footpath around the perimeter of the park and through the woods

  • Boardwalks from recycled plastic

  • Some minor clear out works in the woods to open the space

  • Entrance paths improvements

  • Newly planted tree lined path section to create shade

  • Installation of new bins and benches

The team contracted Maydencroft to deliver these improvements. Several site visits were scheduled throughout the lifecycle of the project with locals and park users giving them the opportunity to learn more about the works taking place.

Once works are fully complete, a launch event will take place autumn/winter 2025.

More information to follow

Project updates:

July 2025 Update*

  • Boardwalk is complete
  • Gravel pathway almost complete
  • Street furniture locations confirmed, due to be installed.

Due to certain events occurring over the summer and the unpredictable weather conditions, project completion is now expected to be in autumn 2025.

May 2025 Update*

  • Tree planting almost complete, final tree planting to be done winter 2025 with the friends.
  • Breedon gravel is being laid out on sub-base along the pathway
  • Boardwalk complete
  • Swales complete
  • Project completion still aiming for Summer 25

(Photos of the pathway, boardwalk and tree planting)

March 2025 Update*

  • Tree planting has begun, with a community planting day held Tuesday 25 February where 15 trees were planted by residents, friends of Ludlow Road Open Space, Councillors, Countryside team and the Parks team. Facilitated by Maydencroft.
  • The subbase for the perimeter pathway has been completed and progress has been made on the boardwalk.
  • The project is expected to be complete by Summer 2025.

November 2024 Update*

Due to the wet weather conditions the completion works have been pushed to end of January.

August 2024 Update*

Ludlow Road Open Space Perimeter Pathway is progressing as per schedule. Maydencroft have been on site for almost a month and have been busy laying the foundations for the beginning of the path network. They have been clearing through some vegetation to join up the path networks near Sycamore Close and will be conducting some minor vegetation clearances through the woodland to allow for the beginning of the boardwalk to commence.


Page last updated: 01 Aug 2025, 10:40 AM